The demolition has progressed as planned and Veit should wrap things up by Friday. The chainlink fence has been moved a few feet west to give us better access from Como Avenue to the playground and main doors. RJM is scheduled to fix the sidewalk and walkway today, and once these are officially open, we can bring the school buses back to Como and also re-open access to our school campus from Como Avenue. We will confirm this change to all families with a separate email from the Front Office once the walkway is ready.
For a quick overview of our project and more detailed safety information, check out this FAQ sheet. It will also be shared with D10 and neighbors.

Andy Nesset

TCGIS Building Manager

Tina Haarbusch