8/22/19 Elternbrief building update

This week the main structure was successfully brought down. Veit has started separating materials and loading them on trucks. There were two places that needed some extra structural support before they could completely remove the brick wall and bottom of the chimney from the new building. The demolition phase is progressing as planned and should last the next 2-3 weeks.

Andy Nesset

TCGIS Building Manager

Tina Haarbusch